Prop 3 Projects: Facilities
In the Rockwood School District, we understand that well-maintained school buildings are the foundation of learning environments essential for student success. Proposition 3 helps responsibly fund facilities priorities such as HVAC system replacements, roof replacements, and other areas of deferred maintenance that were a major focus of the proposition.
Updates and Highlights
Completed
- New HVAC at Ellisville, Kehrs Mill, and Uthoff Valley
- Parking lot at Lafayette, Ballwin walkway
- Ridge Meadows roof
- Green Pines playground
- White fleet and equipment replacements
In Progress
- Rockwood Valley water line
- Rockwood South track
Upcoming
- New HVAC at Bowles, Geggie, Rockwood South, and Westridge
- Roofs at Ellisville, Kehrs Mill, and Uthoff Valley
- Turf at Marquette and Rockwood Summit stadiums
- Flooring, bathrooms, ADA compliance
- Parking lots TBD
Projects are presented below in the year in which they were budgeted. Since most of the district’s capital project work is completed over the summer months, the total project cost may straddle fiscal years. Select each category for a detailed description and further breakdown.
| Description | Project Cost |
|---|---|
| 8,396,578.00 | |
| 3,196,537.00 | |
| 21,630.00 | |
| 556,614.00 | |
| 152,882.00 | |
| 186,119.00 |
| Description | Project Cost |
|---|---|
| 12,121,750.00 | |
| 3,948,674.00 | |
| 1,000,000.00 | |
| 200,000.00 | |
| 1,000,000.00 | |
| 750,000.00 | |
| 200,000.00 | |
| 120,000.00 | |
| 1,000,000.00 | |
| 500,000.00 | |
| 400,000.00 |
In Depth: HVAC Improvements
- HVAC systems greater than 20 years old reduced from 20 to 10 of 37 buildings by Fall 2027
- Total Prop 3 funds spent on HVAC by Fall 2027 will approximate $35 million
- Estimated savings in total bond interest on the 13 completed projects: $10-14 million
| Building/System | Projected Age of HVAC System Fall 2027 | System Improvement with Prop 3 Funding in lifetime years reduced |
|---|---|---|
| Admin Office | 14 | improvement scheduled for future date |
| Admin Annex | 1 | 23 |
| Babler Elem | 10 | improvement scheduled for future date |
| Ballwin Elem | 28 | improvement scheduled for future date |
| Blevins Elem | 1 | 23 |
| Bowles Elem | 2 | 22 |
| CCL | 11 | improvement scheduled for future date |
| Chesterfield Elem | 30 | improvement scheduled for future date |
| Crestview Middle | 28 | improvement scheduled for future date |
| Clarkson Valley EC | 4 | 16 |
| Eureka EC | 31 | improvement scheduled for future date |
| Vandover EC | 28 | improvement scheduled for future date |
| Ellisville Elem | 3 | 21 |
| Eureka Elem | 8 | improvement scheduled for future date |
| Eureka High | 28 | improvement scheduled for future date |
| Facilities/WH | 16 | improvement scheduled for future date |
| Fairway Elem | 1 | 19 |
| Geggie Elem | 2 | 22 |
| Green Pines Elem | 10 | improvement scheduled for future date |
| Kehrs Mill Elem | 3 | 20 |
| Kellison Elem | 24 | improvement scheduled for future date |
| Lafayette High | 1 | 23 |
| LaSalle Middle | 17 | improvement scheduled for future date |
| Marquette High | 13 | improvement scheduled for future date |
| Pond Elem | 26 | improvement scheduled for future date |
| Ridge Meadows Elem | 4 | improvement scheduled for future date |
| Rockwood South Middle | 2 | 21 |
| Rockwood Summit High | 14 | improvement scheduled for future date |
| Rockwood Valley Middle | 17 | improvement scheduled for future date |
| Selvidge Middle | 11 | improvement scheduled for future date |
| Stanton Elem | 27 | improvement scheduled for future date |
| Transportation Shop | 5 | improvement scheduled for future date |
| Uthoff Valley Elem | 3 | 20 |
| Westridge Elem | 2 | 22 |
| Wild Horse Elem | 1 | 24 |
| Wildwood Middle | 26 | improvement scheduled for future date |
| Woerther Elem | 20 | improvement scheduled for future date |
Hover over (or tap on a touch screen) any of the bars in the chart for more details!
Chart is loading...
| Abbreviation | Name |
|---|---|
| ADM | Administrative Center |
| ANX | Administrative Annex |
| BAB | Babler Elementary |
| BLE | Blevins Elementary |
| BOW | Bowles Elementary |
| CCL | Center for Creative Learning |
| CHE | Chesterfield Elementary |
| CMS | Crestivew Middle |
| ECC | Early Childhood: Clarkson |
| ECE | Early Childhood: Eureka |
| ECV | Early Childhood: Vandover |
| ELL | Ellisville Elementary |
| EUR | Eureka Elementary |
| EHS | Eureka High |
| FAC | Facilities |
| FWY | Fairway Elementary |
| GGE | Geggie Elementary |
| GRP | Green Pines Elementary |
| KME | Kehrs Mill Elementary |
| KEL | Kellison Elementary |
| LHS | Lafayette High |
| LSMS | LaSalle Springs |
| MHS | Marquette High |
| PND | Pond Elementary |
| RME | Ridge Meadows Elementary |
| RSM | Rockwood South Middle |
| RSH | Rockwood Summit High |
| RVM | Rockwood Valley Middle |
| SMS | Selvidge Middle |
| STA | Stanton Elementary |
| TRN | Transportation |
| UVE | Uthoff Valley Elementary |
| WST | Westridge Elementary |
| WHE | Wild Horse Elementary |
| WMS | Wildwood Middle |
| WOE | Woerther Elementary |